Monday, July 23, 2018

Roof Reno Days 14-21

We missed watching nearly two weeks worth of work on the roof for family reunion/vacation. While we were away, the blue board insulation was installed, 2x4 air channel strips installed, and the north roof had its decking and ice & water shield installed. The blue board with its 2x4s revealed a sag that had developed in the south roof over the master bedroom. It was jacked up and collar ties installed at 9ft high. The fact that we do not have to hang more dry wall on that tall vaulted ceiling (along with mud, tape, & paint) does not make me sad.